Specific capacity before and after treatment
Nine documented wells from the archive. Pump-test data, gpm/ft.
(combined treatment) = impulse combined with brushing and chlorination. From Flow Industries' documented treatment archive; full records on file. Results depend on site conditions.
Case studies
Detailed treatment records, published as they are prepared.
A new well produced far below design. AirShock® impulse development raised specific capacity from 7.9 to 22.0 gpm/ft — without redrilling.
Read the case study → 93–105% Irrigation · France · rehabilitation · screened wellA well at 3% of its original capacity recovered to 93–105% of its as-built specific capacity — a hydraulic bottleneck, not a water shortage.
Read the case study → +90% · sand < 1 ppm Municipal · US Midwest · sandstone · ~1,500 ftFalling capacity and sand pumping in a deep open borehole: restored from 10.1 to 19.2 gpm/ft, with sand production cut below 1 ppm.
Read the case study → +58% Municipal · US Midwest · sandstone · ~1,070 ftA cable-tool well decades in service, with legacy debris and a borehole bridge, restored from 9.8 to 15.5 gpm/ft.
Read the case study →Want to discuss a specific well or project?
Send us your well construction and pump test data. We will tell you frankly whether impulse treatment fits.